• Client: Prominent AC & Vent Firm based in the midlands.
  • Location: Midlands
  • Value: Value £107k
  • Works: Full public health package including washrooms, HVAC works included the installation of four pipe fan coil.
  • Duration: 3 months

Enhancing HVAC and Utility Infrastructure for Multi-Floor Boutique Serviced Office Space in the City of London, Tudor Street, Blackfriars.

The Client sought to upgrade their office facilities, particularly focusing on improving the Heating, Ventilation, and Air Conditioning (HVAC) systems, utility infrastructure, and sanitary facilities in a multi-floor workspace. The project aimed to create a more comfortable, efficient, and inclusive working environment.

Challenges:

  1. HVAC Enhancement: The existing HVAC system required significant improvement to provide effective cooling and heating for the entire workspace, especially in the free-issue fan coil areas.
  2. Utility Upgrades: The client needed a new tea point with water heating capabilities and a system for handling pumped waste water. This demanded precise planning and installation.
  3. Sanitary Facilities: The client aimed to enhance the restroom facilities, including separate Ladies and Gents WC blocks on two floors, each featuring a Disabled Access WC.

Solution:

A&S Mechanical Engineering was entrusted with this multifaceted project due to our expertise in designing and implementing comprehensive HVAC and utility solutions. We meticulously addressed the client’s requirements:

  1. HVAC Enhancement: A&S designed and installed a robust HVAC system, ensuring that the free-issue fan coils provided efficient cooling and heating. This was achieved through a customised pipework layout, optimised for the specific requirements of the workspace.
  2. Utility Upgrades: We created a state-of-the-art tea point with water heating capabilities and a pumped waste water system, enhancing the overall utility infrastructure. This solution improved convenience and productivity in the workspace.
  3. Sanitary Facilities: Our team designed and constructed separate Ladies and Gents WC blocks on two floors, with a Disabled Access WC on each floor. These facilities were built to the highest standards to ensure inclusivity and compliance with relevant regulations.

Results:

The project’s successful completion transformed the client’s workspace, delivering significant benefits:

  • Improved Comfort: The HVAC enhancements created a more comfortable environment for employees, with better control over temperature.
  • Enhanced Productivity: The utility upgrades, including the new tea point and waste water system, contributed to increased productivity and convenience in daily operations.
  • Inclusivity: The upgraded sanitary facilities, including Disabled Access WC blocks, made the workspace more inclusive, aligning with modern workplace standards.

A&S Mechanical Engineering’s dedication to precise design and expert installation led to a comprehensive transformation of the client’s multi-floor workspace. Our commitment to excellence and attention to detail resulted in an improved, efficient, and inclusive environment for their employees, contributing to the overall success of the project.